Location

Atlanta, GA

Owner

Northside Hospital | Cumming, GA

Architect

HRD | Atlanta, GA

Northside Hospital Forsyth CSPD Renovation

  • 28,000-square-foot renovation and expansion of the existing Central Sterile Department

  • Work was completed in four primary phases and 16 sub-phases and included construction of new decontamination, sterilization, sterile storage, and prep-and-pack areas

  • The project also included construction of a new elevator and shaft, exterior mechanical room, administrative offices, break room, and locker rooms

  • Additional scope included renovation and expansion of existing central energy plant equipment and relocation of an existing electrical room to support the department’s expansion and infrastructure requirements